Transient testing during MEA-3 test campaign

The purpose of the project was to analyze the transient (time-dependent) performance of the amine process. NTNU developed and detailed transient test cases based on process simulations using their dynamic process model of the TCM amine plant.

Vendor
NTNU
Partners
NTNU, TCM
Test at TCM
17-23 July 2017
Financed
NTNU in-kind funding, TCM
Contact at TCM
Nina Enaasen Flø